Table 18: Maintenance Plan/ Shutdown Schedule Description

Project Benefits

Period Implemented 29 May to 2 June 2025

B16 Pipeline connection to Zuikerbosch Water Treatment Plant Station 5 to Engine Room 3 at Mapleton Booster Pumping Station.

To connect the newly constructed B16 pipeline, which will be supplying water from the new Station 5 at Zuikerbosch Water Treatment Plant to Engine Room 3 at Mapleton Booster Pumping Station.

Disconnect and remove pump set 5 for overhaul at Amanzimtoti Pumping Station. Russel Road meter installation.

To improve the reliability and performance of the pump.

29 May 2025 to 30 May 2025

Installation of a new meter to alleviate challenges of water supply around Primrose. Minimise water losses in the Rand Water network that contribute to Non-Revenue Water. Maintenance of plant equipment will increase and maintain plant availability, reliability and improved efficiency. Minimise water losses in the Rand Water network that contribute to Non Revenue Water.

3 June 2025

Zwartkopjes Station valves replacements.

30 June to 2 July 2025

Pipe leak repairs at Zuikerbosch affecting Eikenhof System.

30 June 2025 to 2 July 2025

INFRASTRUCTURE HIGHLIGHTS Eikenhof Flexibility Project

• Optimise the operation and utilisation of pump sets during isolations. • Endeavour to ensure Peak Day Pumping Demand is met. • Minimise disruptions to water supply for the customers. The revised estimated project completion date is February 2026 with only the electrical work; automation work and minor civil works being finalised. Progress thus far has enabled the pumping station to be 100% flexible with Engine rooms 2 and 3 having 100% flexibility.

The project entails design, manufacturing, supply, delivery, installation, commissioning and putting into service of 14 new suction and delivery header isolation valves and one (1) flow control valve complete with associated pipework and pipe specials at Rand Water Eikenhof Pumping Station. The installation will benefit Rand Water by: • Creating pumping flexibility to allow isolation of at least one (1) half of the Engine room pump sets to carry out required maintenance work on pump sets while continuing the supply through the other half.