DST 4th Edition Handbook INTERACTIVE

No. SERVICES ROLES AND RESPONSIBILITIES SUPPLY CHAIN MANAGEMENT Bid administration (Procurement above R1 000 000) 5. SCM requests DDG approval to

RESPONSE TIME ACCOUNTABILITY ESCALATION

Within two days of receiving budget confirmation. Within two weeks after the Committee has received the specifications.

appoint both Bid Specifications (BSC) and Bid Evaluation Committee (BEC).

6. Bid Specification Committee convenes, reviews, provides inputs, and approves the TORs.

7. SCM advertises the bid.

Within seven working days

after BSC approval.

8. SCM receives proposals from service providers. 9. SCM reviews the proposals received and prepares documents for evaluation. 10. BEC meets to evaluate received bids and recommends the service provider.

21 days post the advert. Within two days.

Within 40 days DD: SCM

DD: SCM Scm.escalations@ dst.gov.za