Health - - 2 - -2 Projects were not completed due to: • Helen Joseph: Delay in implementation of
contractors’ invoices by GDoH delayed the payments and the delivery of the LV
contractor’s lien over the site. • Chris Hani Baragwanath Hospital: Contractor’s
court orders which led to the contractor enforcing his
cash flow problems and the delays on the
panels, completion
of the outstanding scope. STARS 1 1 4 4 - Not Applicable
Reasons for deviations
Education 5 5 21 13 -8 The following projects were not completed due to late
appointment of contractors. • Sundown High School • Laerskool Parksig • Goudweskool
• Laerskool Handhawer • Tshirela Primary School • Kokosi Primary School • Laerskool Noordhoek
The following project was not completed due to
delays in approval of tender documents at Bafikile Primary School.
from planned target to Actual
Deviation
Achievement 2023/2024
**Actual
Achievement 2023/2024
Target
Annual
Planned
2023/2024
Actual
Audited
Performance 2022/2023
Actual
Audited
Performance 2021/2022
Output
Indicator
Programme / Sub-programme: Outcome Output
58