DID ANNUAL REPORT 2022 23
Annual Report 2022-2023
1. AUDITOR-GENERAL’S REPORT: PREDETERMINED OBJECTIVES The AGSA currently performs certain audit procedures on the performance information to provide reasonable assurance in the form of an audit conclusion. The audit conclusion on the performance against predetermined objectives is included in the report to management, with material findings being reported under the Predetermined Objectives heading in the Report on other legal and regulatory requirements section of the auditor’s report.
Refer to page 168 of the Report of the Auditor-General, published as Part F: Financial Information.
2. OVERVIEW OF DEPARTMENTAL PERFORMANCE 2.1. Service Delivery Environment
During the 2022/23 financial year, the department has implemented several projects on behalf of client departments being the Department of Health, Education and Social Development, Sports, Arts, Culture and Recreation and Roads and Transport. In projects’ implementation, the department has faced several issues pertaining to changes in scope of the projects, cashflow problems of the contractors, community unrests causing delays in completion of these projects. Some of these challenges, at times, have resulted with contractors abandoning the sites. The bleak global economic outlook has resulted in limited budget allocation for projects, which has affected the implementation. The Department continuously provides support to emerging contractors through the Contractor Development Programme (CDP). The CDP is aimed at transferring skills for emerging contractors in the infrastructure sector to ensure they possess adequate technical skills and experience needed to implement projects.
2.2. Service Delivery Improvement Plan
The Department has completed a service delivery improvement plan. The tables below highlight the service delivery plan and the achievements to date.
Main services and standards Main services
Beneficiaries
Current/actual standard of service
Desired standard of service 20 properties to be transferred to third parties 6 properties to be released for socio economic
Actual achievement
Increase the number of GPG properties to be leased out to interested parties for revenue generation.
GPG Client Departments, Local Municipalities, Parastatals, Citizens, and Communities
5 properties disposed of
13 properties transferred to third parties 6 properties were for socio-economic
3 properties released for socio-economic
infrastructure development
infrastructure development
infrastructure development
9 facilities provided to user departments (fit for purpose)
8 facilities provided to user departments (lease)
12 facilities provided to user departments
34
DEPARTMENT OF INFRASTRUCTURE DEVELOPMENT
Made with FlippingBook - Online magazine maker