RAND WATER ANNUAL REPORT 2023
HOW WE CREATE VALUE
Project name
Refurbishment of Pump Station 2
Contract Description:
The scope of work entails refurbishing the mechanical and electrical equipment, the emergency dam, the structural and building works including the access and safety equipment, and the civil works which include the driveway paving and fencing.
Project Progress
The overall project progress is 82.2% completed.
Project name
Mechanical & Electrical Repairs at Leeuwkuil wastewater treatment plant
Contract Description:
Mechanical and electrical repairs for the functionality of the wastewater treatment plant–Inlet works (repairs of mechanical & and coarse screens, Grit Classifier, conveyance, and gearbox.
Project Progress
All mechanical & and electrical repairs for the inlet are 100% completed.
Project name
Mechanical & Electrical Repairs Sebokeng Wastewater Treatment Plant
Contract Description:
Mechanical and electrical repairs of Head of works, Primary settling tanks, Bioreactor, Settling Tanks, and Chlorine Systems. Both inlet works and primary settling tanks for Modules 3 and 4 are 100% complete while the chlorine system is 50% complete. Module 5 BNR is 100% complete while the chlorine system is 100 % complete.
Project Progress
Project name
Construction of Rothdene pump station rising main in Meyerton, Gauteng
Contract Description:
Construction of 4.7km of 900mm HDPE Rothdene pump station rising main.
Project Progress
Project status: 100% complete.
Project completion date: 12 December 2022. The next phase of s63 intervention will focus on the construction of capital projects to increase the capacity of the sanitation infrastructure for current and future demands.